To simplify the work during the preparation of the detail documentation for projects, the engineers at AUTEL have developed and programmed an application that can be used as a tool for data administration. This tool is used for work in AUTEL and enables: administration of…
AUTEL designs 110 kV substationAUTEL, a.s. participated in the tender for the project “MoRe sub-stations T4 110 kV” in ENERGETIKA TŘINEC, a.s. (ET) and submitted its bid for the complex solution. After several revisions and demanding technical – trade negotiations and presentations, the Board of Directors decided to split the…
Replacement of Ladle Furnace ControlAUTEL implements replacement works on the control system ABB AC 410 of the ladle furnace PK5 for a new control system Siemens Simatic in the Polish company Celsa "Huta Ostrowiec" Sp. z o.o. In the context of replacement of the existing system, in addition to…
Reconstruction of the control system for blast furnace VP2At present, blast furnace VP2 in ArcelorMittal Ostrava is controlled by the Centum CS3000 system from the firm Yokogawa, and is close to the end of its service life. The client needed to decide between reconstructing the existing Centum system or replacing it with a…
K13 Boiler Denitrification in VeoliaAt the beginning of February 2014, the AUTEL company signed a contract with SLOVENSKÉ ENERGETICKÉ STROJÁRNE (SES) for the project "Denitrification of K14, K13, K12 boilers" in Veolia Energie ČR. The contract included the following: technological heavy current HV, LV, instrumentation and control system for…
Turbine 38 MW, Morupule, BotswanaThe coal power plant located near Palapye in the Central District in Botswana, no longer operational and known among the local population as the “ghost factory” will be commissioned by the Doosan Heavy Industries and Construction over the next two years. The Morupule A power…
Control systems for turbines in the USAAUTEL has been awarded a contract to deliver two control systems for turbines manufactured by Siemens, s.r.o., Industrial Turbomachinery. The two turbines with the output of 35 MW and 11 MW, respectively, will generate electricity in California in the USA. The CZK 5 million contract…
32 MW Turbine, MazidagiSNC Lavalin is the main contractor for the Mazidagi Fertilizer Complex project for the Turkish company ETI BAKIR A.S. The supplier of the 32 MW turbine as the “package unit” for this project is DOOSAN ŠKODA POWER, s.r.o. DOOSAN ŠKODA POWER evaluated the bid from…
375 MW Turbine, Red Dragon, PIEM project, ChileThe South Korean company SK Engineering & Construction (SK E&C) builds a new block in the existing Mejillones Power Plant standing in the gulf on the shore of southern Pacific Ocean in the Chilean province of Antofagasta. The output of the block is planned to…
AUTEL is upgrading the control system of the papermaking machineMondi Świecie S.A. v Świeciu, a company in Poland, is carrying out the project of modernizing its papermaking machine MP1. The required technological adjustments will be made by the Finnish company Valmet. Part of the current modernization efforts is the replacement of the obsolete control system…